Change orders are a fact of life in construction. Improve profitability, cash flow and customer satisfaction by effectively managing changes. Build a foundation for success with 12 steps to improve pricing and 11 negotiating strategies for the whole project team.
 D. Brown Management
            
            February 24, 2019
            
                    D. Brown Management
            
            February 24, 2019
        The first step for contractors improving their management of changes on a project is simply earlier identification. This starts with a better definition of what a change really is, and then setting standards within your company around that definition.
change management foreman training project management D. Brown Management
            
            March 11, 2019
            
                    D. Brown Management
            
            March 11, 2019
        Changes are a part of the construction process with many underlying causes. While we have all heard the average of 10% changes on construction projects, it is interesting to look at an industry study for validation.
change management foreman training project management D. Brown Management
            
            March 12, 2019
            
                    D. Brown Management
            
            March 12, 2019
        A 10% improvement in change order pricing for a $50M per year contractor will add $500K to their bottom line. This is not about simply marking up the change more, but rather, including the many costs that are typically missed or undervalued.
change management financial management foreman training project management D. Brown Management
            
            March 13, 2019
            
                    D. Brown Management
            
            March 13, 2019
        Construction is a cash-intensive business and change orders are often one of the root causes of poor cash flow. A 30-day improvement to change management workflow can generate over $400K in additional cash flow for a $50M contractor.
cash flow change management financial management foreman training project management D. Brown Management
            
            March 14, 2019
            
                    D. Brown Management
            
            March 14, 2019
        If you perceive that changes are a problem in construction, then you are likely framing them as a point of blaming others. This framing will impact your ability to effectively manage changes.
business management change management foreman training leadership principles project management wisdom D. Brown Management
            
            May 3, 2020
            
                    D. Brown Management
            
            May 3, 2020
        Projects are complex with evolving requirements and changing site conditions. Mistakes will be made. It is how the collective project team manages these changes that ultimately determines success at all levels.
change management preconstruction project management project planning D. Brown Management
            
            March 15, 2019
            
                    D. Brown Management
            
            March 15, 2019
        Start improving your change management skills by creating some categories of the underlying causes of changes your company experiences.
change management foreman training preconstruction project management project planning D. Brown Management
            
            March 16, 2019
            
                    D. Brown Management
            
            March 16, 2019
        Contractors don't typically see the full negative impact of changes and, therefore, don’t put the right level of resources into their management.
cash flow customer satisfaction estimating financial management foreman training labor productivity project management D. Brown Management
            
            March 18, 2019
            
                    D. Brown Management
            
            March 18, 2019
        For contractors to manage changes effectively, they must understand the entire change management workflow up through the project owner’s approval and payment process.
business management cash flow change management foreman training project management value stream workflow mapping D. Brown Management
            
            March 19, 2019
            
                    D. Brown Management
            
            March 19, 2019
        Managing changes effectively means that you need clear visibility across all projects. While the workflow will vary by project, the key progress milestones in your internal process will remain fixed.
business management change management process standardization project management D. Brown Management
            
            March 28, 2019
            
                    D. Brown Management
            
            March 28, 2019
        Great change management starts with a good tracking system. The far more important part of change management is the rigorous review process at least 2X monthly with your PMs that will limit your risk, increase your opportunities, and train your team.
change management financial management process standardization project management technology D. Brown Management
            
            March 29, 2019
            
                    D. Brown Management
            
            March 29, 2019
        Summarize your detailed change tracking logs with concise dashboards that give you critical information in a format that allows you to see the big picture while still having enough information to be actionable.
business management change management process standardization project management technology D. Brown Management
            
            April 5, 2019
            
                    D. Brown Management
            
            April 5, 2019
        There are four foundational items that support great change management. Without these in place, you will never get the value out of streamlining the process.
communication contract management estimating market strategy negotiating opportunity selection preconstruction D. Brown Management
            
            April 8, 2019
            
                    D. Brown Management
            
            April 8, 2019
        Early identification of changes and conflicts is the first key to success. The capability to identify changes and conflicts early in the process is a combination of organizational structure, systems, management, training, and coaching.
cash flow customer satisfaction estimating foreman training labor productivity preconstruction project management project planning D. Brown Management
            
            April 15, 2019
            
                    D. Brown Management
            
            April 15, 2019
        The ability to identify potential changes early is a skill that can be tested, trained, and managed just like a craft skill.
change management foreman training project management talent development D. Brown Management
            
            April 22, 2019
            
                    D. Brown Management
            
            April 22, 2019
        Few things will improve customer satisfaction, profitability, cash flow, risk, and team stress more than early identification of change orders. This is a process and a trainable skill. Checklists are some of the most valuable tools in that process.
change management project management D. Brown Management
            
            February 12, 2020
            
                    D. Brown Management
            
            February 12, 2020
        The business of construction is filled with constant problems. It’s not that great contractors don’t have problems, it's that great contractors have learned how to troubleshoot first, which allows them to learn from their problems faster.
principles problem solving wisdom D. Brown Management
            
            August 25, 2018
            
                    D. Brown Management
            
            August 25, 2018
        Contractors are continually faced with costly impacts to their labor productivity and schedule with many beyond their direct control. The best Project Managers know how to identify, communicate, and mitigate these impacts.
business management change management foreman training labor productivity negotiating project management D. Brown Management
            
            April 20, 2019
            
                    D. Brown Management
            
            April 20, 2019
        Some of the impacts you see on a project are not as clear as a design change, conflict, or obviously changed condition. Some impacts, such as poor project sequencing or congested work areas are hard to notice if you don’t have good tracking systems.
budget management change management foreman training project management project planning schedule management D. Brown Management
            
            March 7, 2018
            
                    D. Brown Management
            
            March 7, 2018
        Maximizing labor productivity starts with defining exactly what needs to be delivered and then breaking it down into tasks that can be effectively managed.
change management foreman training labor productivity project management project planning schedule management D. Brown Management
            
            September 2, 2018
            
                    D. Brown Management
            
            September 2, 2018
        There are two critical key results that should be focused on as part of every project planning process.
budget management change management foreman training labor productivity project management project planning schedule management D. Brown Management
            
            September 4, 2018
            
                    D. Brown Management
            
            September 4, 2018
        Schedule + Production are two foundational key results the Foreman will achieve through their planning. The heart of any production measurement is simply “Earned Budget vs. Actual Cost”.
budget management labor productivity production tracking project management schedule management technology D. Brown Management
            
            August 24, 2018
            
                    D. Brown Management
            
            August 24, 2018
        Effective planning processes are the foundation for great production. The planning process can be seen as a series of tighter and tighter concentric circles with the bullseye being the daily plan. Daily feedback improves performance and mitigates risk.
change management foreman training labor productivity