Production Tracking - Changing the Language

Your productivity will start to really improve as it becomes a culture and not just a tracking system.

D. Brown Management Profile Picture
Share
Field Productivity: Troubleshooting Problems when Production Tracking.

You will first notice this as a change in language in the field and across the whole project team:

--- EXAMPLE ---

FROM:  The job superintendent is disorganized and skipping us all over the project.

TO:  We are being moved all over the job site due to plan coordination errors.  Our framing productivity has been 78% of target for the last 3 days.  


How do you talk?

How does your team talk?

What can you do to improve?

What would that be worth?


Improving Labor Productivity Workshop


Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Production Tracking - Changing the Language
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Rubber Ducks for Planning and Troubleshooting Effectively
"If you can't explain it simply, you don't understand it well enough." - Albert Einstein Wisdom that is as applicable to physics as it is to being a Foreman, Project Manager, or Owner of a construction company.
Impacted Productivity - Dilution of Management
Dilution of management will compound an already impacted construction project. It is important for teams to realize the full costs of impacts as they start to occur.
First of a Kind: Managing to Accelerate Outcomes and Mitigate Risks
Special attention is required for all "First of a Kind" projects, job roles, processes, and tools. This is often overlooked, slowing down progress and creating unnecessary risks for contractors.