Labor Productivity - How Much Could You Save?

Winners of the construction labor productivity is a game focus on minutes and seconds.

D. Brown Management Profile Picture
Share

They focus on the smallest details of every movement looking at ways to eliminate waste while lowering the burden on the labor and increasing reliability.

Field Productivity: Labor Productivity - How Much Could You Save? Graph representing annual field labor cost and additional productive minutes per day.

There are 480 minutes in an 8 hour shift.  During the typical construction day only 307 of those minutes are spent actually installing materials.  


How much could you save if you got very deliberate with your training and execution over the next year?

Improving Labor Productivity Workshop


Labor Productivity - How Much Could You Save?
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Labor Productivity - How Much Could You Save?
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Aligning Strategic Market Choices and Project Delivery Methods
Choosing which market(s) to compete in and which to avoid are the most highly leveraged decisions the leaders of construction businesses make. Integrated with those is choosing the optimum project delivery method(s) to focus on.
Builder and Business Manager Integration
A successful and sustainably growing construction business has the right balance of builder and business manager skills on the team.
9 Ownership Transition Issues Specific to Contractors
All businesses face challenges with an ownership transition. There are nine interrelated issues that heavily impact contractors.