Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)

The biggest risk for a specialty contractor is the performance of on-site labor.

D. Brown Management Profile Picture
Share

One of the biggest impacts to labor productivity is having a schedule that requires large variations in labor. The most ideal situation is to have a steady ramp up, stable crew size during peak production followed by a steady demobilization.

Field Productivity: Impacts - Unleveled Manpower Schedule.

 

No project will be perfect and impacts to highly variable labor requirements include:

  • Overloading the project to meet demands resulting in too many people during downtimes, which then lowers productivity.  
  • Learning curve for new team members coming on and off the project. Studies show that productivity can be impacted by as much as 10% during the first week for a craftsperson learning a new project. 
  • Overtime required to meet the schedule. Not only will you have the increased cost per hour, but you will experience a decrease in productivity and safety. Four weeks at 5-10’s will impact productivity by 20%.
  • Poor scheduling often goes hand-in-hand with stacking of trades which can cost another 10-50% decrease in productivity for those areas.  
  • There is an increase in the coordination time it takes to move manpower on and off the project which has a direct cost as well as an indirect cost from dilution of management.  

 

 

 


Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Impacted Productivity - Highly variable Labor Scheduling (Level Your Schedule)
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Lean Principle - Kaizen (Every Detail Matters)
As contractors build their businesses, it is important to look at every detail from the first meeting with a potential customer through winning and building the project. This same attention to detail also applies to supporting operations and talent.
Continuous Improvement: Plan, Do, Check, and Act (PDCA)
Improving productivity in construction is exceptionally challenging. It must be embraced as a journey and not a destination. It must be made into a game so that people clearly see what winning looks like and fall in love with the process.
Underlying Causes of Changes on Projects
Start improving your change management skills by creating some categories of the underlying causes of changes your company experiences.