Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process

A basic Schedule-of-Values (SOV) with flat billings and normal collection processes will yield about a 30% return on capital over the first 12 months of a project when looking at it from a cash basis.

D. Brown Management Profile Picture
Share

This is in the average-high range for contractors, depending on type.  

Cash Flow: Tip 14 Aggressive Billings - Pre-Wiring for Success. From a 12-month 31% return-on-capital at risk which is the high-average for contractors up to a 49% or greater return. Punch-as-You-Go Ensuring Maximum Monthly Billings Percentage of Completions “Sold” Ahead of Billing Change Order Approvals Contractually Required Support Documents Verified Early

Our focus is helping contractors achieve performance in the upper end of their peers, including cash flow. Look at the differences that aggressive management of every aspect of billings can make:

 


Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Related Training
Cash Flow Tip 14 - Aggressive Billings and Pre-Wiring the Process
Great cash flow is a key driver of valuation and successful successions. Running out of cash is is the #1 reason contractors fail. Improving cash flow improves your Return on Equity. Protect yourself and never let cash flow be the limitation to your profitable growth....

Levels of the Value Stream
For contractors to unlock maximum value during business development, preconstruction and project execution it is critical to understand the broader value stream of the project beyond their scope. 10 levels of granularity in the construction value stream:
Making Decisions Effectively
What would it be worth for your company if you could accelerate the development of your leadership talent?
The Role of Key Subcontractors and Vendors in the Preconstruction Process
Subcontractors and vendors are positioned to add a lot of value during the preconstruction phase. Unfortunately few of them actually deliver that value. Learn why and what to do about it.